Sobha Neopolis Phase 5 (Wings 5, 6 and 7)
By Sobha in Panathur (Bengaluru East), Bengaluru, 560103
- Status
- Under construction
- Type
- Residential
- Locality
- Panathur (Bengaluru East)
- RERA completion
- 31 Dec 2031
- Total homes
- 302
- Last verified
- 24 Oct 2026
Summary
Approvals and checks: 9 clear, 2 to check, 0 problems. See the full list.
Construction is 73% complete as of 30 Sept 2026.
Project facts
- Type
- Residential
- RERA number
- PRM/KA/RERA/1251/446/PR/200923/006271
- Project start (per RERA)
- 1 Apr 2024
- Promised possession
- Not available
- RERA completion date
- 31 Dec 2031
- RERA extension
- No extension recorded
- Commencement certificate (CC)
- Not on RERA
- Occupancy certificate (OC)
- Not yet due
- Land area
- 2.55 acres118 homes per acre
- Open area
- 74.2% of the site
- FAR sanctioned
- 2.99
Location
Panathur (Bengaluru East), Bengaluru, 560103
Approvals and checks
9 clear, 2 to check, 0 problems
- ✓RERA registrationRegistered
- ✓Building planApproved by BBMP
- !Commencement certificateNot uploaded on RERA
- –Occupancy certificateDue at completion
- ✓Environmental clearanceFiled on RERA
- ✓Fire NOCFiled on RERA
- ✓Airport height (AAI)Filed on RERA
- –Defence clearance (IAF)Not listed on RERA
- ✓Draft sale agreementPublished on RERA
- ✓Land litigationNone declared by promoter
- ✓Land ownershipPromoter's own land
- ✓KhathaA Khatha
- !Court-records checkPending
Legal cases
No litigation is declared on the land on RERA. RERA lists 2 complaints on this project, both disposed by the Authority.
Legal check not done yet. We have not completed a court-records check for this project.
RERA complaints
2 complaints on this project.
What complaints were about
One complaint can raise several issues, so issues add up to more than the number of complaints.
By year filed
Disposed Pending
See all 2 complaints
- Alleged wrong flat allocation, misuse of signed documents and deduction from the booking amount
- Booking amount refund with interest for the delay
Construction and sales
From the promoter’s latest RERA filing, as of 30 Sept 2026.
By tower
Construction complete Homes sold
Over time
Construction complete Homes sold
- Collected from buyers
- Rs 10.61 Cr
- Withdrawn from the RERA account
- Rs 13.29 Cr
- Total project cost (as declared on RERA)
- Rs 410.05 Cr
Construction timeline
Bars show the promoter’s planned dates on RERA. The vertical line is today. Colour shows progress from the promoter’s latest RERA filing.
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
77% complete
74% complete
77% complete
93% complete
65% complete
68% complete
100% complete
70% complete
0% complete
53% complete
5% complete
Completed In progress Not started
Units
- Total homes
- 302
- Towers
- 3
- Floors (tallest tower)
- 18
- Unit types
- 3 BHK
- Unit sizes (carpet area)
- 1,132 to 1,241 sq ft
- Unit mix
- 3 BHK: 302
Price
- Price range
- Not available
- Price per sq ft
- Not available
Parking
- Covered parking
- 422 spaces1.4 spaces per home
Amenities
- Clubhouse
- Community hall
- Outdoor sports
- Indoor sports
- Swimming pool
- Parks
- Power backup
Living here
- Water source
- Tanker
- Piped gas
- No
- Kitchen cabinets and wardrobes
- Not stated
- Clubhouse
- 53,820 sq ft178 sq ft per home
Promoter and land
- Builder (brand)
- Sobha
- Registered promoter
- Sobha Limited
- Land owner
- Sobha Limited
- Land arrangement
- Own land
Promoter complaints
- Complaints on the promoter (total)
- 226
- Complaints on the promoter (pending)
- Not available
Sources
Karnataka RERA project page PRM/KA/RERA/1251/446/PR/200923/006271 (registration tabs, Complaints tab and the quarterly updates for Q3 2025-26, Q4 2025-26, Q1 2026-27 and Q2 2026-27, checked 24 Oct 2026).
Things to know
- This record covers Phase 5 as registered on RERA (Wings 5, 6 and 7); the other Sobha Neopolis phases are separate registrations.
- The launch date is the project start date declared on RERA (1 Apr 2024); RERA approved the registration on 20 Sep 2023, and the plan is the same BBMP plan as the other Neopolis phases.
- RERA lists 304 inventory lines, of which 2 are electrical rooms; the 302 homes are all 3 BHK (carpet 105 to 115 sq m), matching the 302 units in the quarterly updates.
- The land is own land of Sobha Limited (A Khatha, BBMP, 22 Dec 2022); no JDA; the promoter's non-litigation affidavit is uploaded and no land litigation is declared.
- Source of water is tankers.
- The land area is the total area of land declared (10,322 sq m).
- RERA lists 422 covered and 30 open parking spaces; the parking totals in the quarterly update add up to 302.
- The commencement certificate is shown as not on RERA, as for the other Neopolis phases.
- Progress as filed was 29% (Q3 2025-26), 73% (Q4 2025-26), 73% (Q1 2026-27) and 73% (Q2 2026-27, filed 14 Oct 2026), so it is unchanged for three quarters.
- All three wings are reported at 100% in the latest update.
- In the Q2 2026-27 schedule the frame, masonry and plastering items are at 100% while their planned start is 26 Sep 2027 or later, as filed.
- The amount withdrawn is higher than the amount collected in Q1 2026-27 (Rs 49.60 Cr against Rs 34.24 Cr) and Q2 2026-27 (Rs 13.29 Cr against Rs 10.61 Cr), as filed.
- RERA's Complaints tab (checked 24 Oct 2026) shows 2 complaints on this project, both disposed by the Authority, and 226 on the promoter; how many of those 226 are pending is not shown.
- Kitchen cabinets and wardrobes are not stated on RERA, although the schedule lists a wardrobe, showcase and kitchen item.
- Quarterly update compliance for earlier quarters not reviewed.
Verification
Last verified 24 Oct 2026