Sobha Neopolis Phase 2 (Wings 12 and 13)
By Sobha in Panathur (Bengaluru East), Bengaluru, 560103
- Status
- Under construction
- Type
- Residential
- Locality
- Panathur (Bengaluru East)
- RERA completion
- 31 Dec 2030
- Total homes
- 225
- Last verified
- 16 Oct 2026
Summary
Approvals and checks: 9 clear, 2 to check, 0 problems. See the full list.
Construction is 47% complete as of 30 Sept 2026.
Project facts
- Type
- Residential
- RERA number
- PRM/KA/RERA/1251/446/PR/200923/006270
- Project start (per RERA)
- 1 Jan 2024
- Promised possession
- Not available
- RERA completion date
- 31 Dec 2030
- RERA extension
- No extension recorded
- Commencement certificate (CC)
- Not on RERA
- Occupancy certificate (OC)
- Not yet due
- Land area
- 4.32 acres52 homes per acre
- Open area
- 89.2% of the site
- FAR sanctioned
- 2.99
Location
Panathur (Bengaluru East), Bengaluru, 560103
Approvals and checks
9 clear, 2 to check, 0 problems
- ✓RERA registrationRegistered
- ✓Building planApproved by BBMP
- !Commencement certificateNot uploaded on RERA
- –Occupancy certificateDue at completion
- ✓Environmental clearanceFiled on RERA
- ✓Fire NOCFiled on RERA
- ✓Airport height (AAI)Filed on RERA
- –Defence clearance (IAF)Not listed on RERA
- ✓Draft sale agreementPublished on RERA
- ✓Land litigationNone declared by promoter
- ✓Land ownershipPromoter's own land
- ✓KhathaA Khatha
- !Court-records checkPending
Legal cases
No litigation is declared on the land on RERA. RERA lists 1 complaint on this project, disposed by the Authority.
Legal check not done yet. We have not completed a court-records check for this project.
RERA complaints
1 complaint on this project.
What complaints were about
One complaint can raise several issues, so issues add up to more than the number of complaints.
By year filed
Disposed Pending
See all 1 complaint
- Cancellation done and refund awaited
Construction and sales
From the promoter’s latest RERA filing, as of 30 Sept 2026.
By tower
Construction complete Homes sold
Over time
Construction complete Homes sold
- Collected from buyers
- Rs 52.31 Cr
- Withdrawn from the RERA account
- Rs 1.61 Cr
- Total project cost (as declared on RERA)
- Rs 308.22 Cr
Construction timeline
Bars show the promoter’s planned dates on RERA. The vertical line is today. Colour shows progress from the promoter’s latest RERA filing.
100% complete
100% complete
0% complete
0% complete
82% complete
0% complete
0% complete
1% complete
7% complete
1% complete
36% complete
0% complete
0% complete
0% complete
0% complete
0% complete
0% complete
0% complete
Completed In progress Not started
Units
- Total homes
- 225
- Towers
- 2
- Floors (tallest tower)
- 18
- Unit types
- 3 BHK
- Unit sizes (carpet area)
- 1,132 to 1,453 sq ft
- Unit mix
- 3 BHK: 225
Price
- Price range
- Not available
- Price per sq ft
- Not available
Parking
- Covered parking
- 308 spaces1.37 spaces per home
Amenities
- Clubhouse
- Community hall
- Outdoor sports
- Indoor sports
- Swimming pool
- Parks
- Power backup
Living here
- Water source
- Tanker
- Piped gas
- No
- Kitchen cabinets and wardrobes
- Not stated
- Clubhouse
- 53,820 sq ft239 sq ft per home
Promoter and land
- Builder (brand)
- Sobha
- Registered promoter
- Sobha Limited
- Land owner
- Sobha Limited
- Land arrangement
- Own land
Promoter complaints
- Complaints on the promoter (total)
- 225
- Complaints on the promoter (pending)
- Not available
Sources
Karnataka RERA project page PRM/KA/RERA/1251/446/PR/200923/006270 (registration tabs, Complaints tab and the quarterly updates for Q3 2025-26, Q4 2025-26, Q1 2026-27 and Q2 2026-27, checked 16 Oct 2026).
Things to know
- This record covers Phase 2 as registered on RERA (Wings 12 and 13); Phase 1 (Wings 14 to 19) is a separate registration.
- The launch date is the project start date declared on RERA (1 Jan 2024); RERA approved the registration on 20 Sep 2023.
- RERA lists 226 inventory lines, of which 1 is an electrical room; the 225 homes are all 3 BHK (carpet 105 to 135 sq m), matching the 225 units in the quarterly updates.
- The land is own land of Sobha Limited (A Khatha, BBMP, 22 Dec 2022); no JDA; the promoter's non-litigation affidavit is uploaded and no land litigation is declared.
- Plan approved by BBMP (BBMP/Addl.Dir/JDNORTH/0003/23-24, 5 Sep 2023, the same plan as Phase 1).
- Source of water is tankers.
- The land area is the total area of land declared (17,488 sq m).
- RERA lists 308 covered and 22 open parking spaces; the parking totals in the quarterly update add up to 225.
- The commencement certificate is shown as not on RERA, as for Phase 1.
- Progress as filed was 30% (Q3 2025-26), 40% (Q4 2025-26), 45% (Q1 2026-27) and 47% (Q2 2026-27, filed 14 Oct 2026).
- Wing 12 is reported at 76% and Wing 13 at 87% in the latest update.
- In the Q2 2026-27 schedule the plinth-level and sub-structure flooring items are at 0% while the frame is 82% complete, as filed.
- The amount withdrawn is slightly higher than the amount collected in Q3 2025-26 (Rs 16.61 Cr against Rs 16.31 Cr), as filed.
- RERA's Complaints tab (checked 16 Oct 2026) shows 1 complaint on this project, disposed by the Authority (a refund after cancellation), and 225 on the promoter; how many of those 225 are pending is not shown.
- Kitchen cabinets and wardrobes are not stated on RERA, although the schedule lists a wardrobe, showcase and kitchen item.
- Quarterly update compliance for earlier quarters not reviewed.