Sobha Dream Gardens Phase 5 (Wing 10)
By Sobha in Bellahalli, Yelahanka Hobli (Bengaluru North), Bengaluru, 560056
- Status
- Under construction
- Type
- Residential
- Locality
- Bellahalli, Yelahanka Hobli (Bengaluru North)
- RERA completion
- 31 Dec 2028
- Total homes
- 142
- Last verified
- 24 Oct 2026
Summary
Approvals and checks: 9 clear, 2 to check, 0 problems. See the full list.
Construction is 97% complete as of 30 Sept 2026.
Project facts
- Type
- Residential
- RERA number
- PRM/KA/RERA/1251/309/PR/311222/005591
- Project start (per RERA)
- 1 Oct 2023
- Promised possession
- Not available
- RERA completion date
- 31 Dec 2028
- RERA extension
- No extension recorded
- Commencement certificate (CC)
- Received
- Occupancy certificate (OC)
- Not yet due
- Land area
- 1.19 acres119 homes per acre
- Open area
- 84.1% of the site
- FAR sanctioned
- 2.38
Location
Bellahalli, Yelahanka Hobli (Bengaluru North), Bengaluru, 560056
Approvals and checks
9 clear, 2 to check, 0 problems
- ✓RERA registrationRegistered
- ✓Building planApproved by BBMP
- ✓Commencement certificateReceived
- –Occupancy certificateDue at completion
- ✓Environmental clearanceFiled on RERA
- ✓Fire NOCFiled on RERA
- ✓Airport height (AAI)Filed on RERA
- –Defence clearance (IAF)Not listed on RERA
- ✓Draft sale agreementPublished on RERA
- ✓Land litigationNone declared by promoter
- !Land ownershipJoint development with landowners
- ✓KhathaA Khatha
- !Court-records checkPending
Legal cases
RERA's Complaints tab (checked 24 Oct 2026) shows no complaints on this project.
Legal check not done yet. We have not completed a court-records check for this project.
RERA complaints
No complaints recorded on this project.
Construction and sales
From the promoter’s latest RERA filing, as of 30 Sept 2026.
By tower
Construction complete Homes sold
Over time
Construction complete Homes sold
- Collected from buyers
- Rs 5.43 Cr
- Withdrawn from the RERA account
- Rs 5.57 Cr
- Total project cost (as declared on RERA)
- Rs 89.62 Cr
Construction timeline
Bars show the promoter’s planned dates on RERA. The vertical line is today. Colour shows progress from the promoter’s latest RERA filing.
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
100% complete
0% complete
100% complete
100% complete
Completed In progress Not started
Units
- Total homes
- 142
- Towers
- 1
- Floors (tallest tower)
- 17
- Unit types
- 1 BHK; 2 BHK
- Unit sizes (carpet area)
- 412 to 627 sq ft
- Unit mix
- 1 BHK: 74; 2 BHK: 68
Price
- Price range
- Not available
- Price per sq ft
- Not available
Parking
- Covered parking
- 164 spaces1.15 spaces per home
Amenities
- Outdoor sports
- Swimming pool
- Parks
Living here
- Water source
- BWSSB
- Piped gas
- No
- Kitchen cabinets and wardrobes
- Not stated
- Clubhouse
- Not available
Promoter and land
- Builder (brand)
- Sobha
- Registered promoter
- Sobha Limited
- Land owner
- Legal heirs of Zahed Husain (Sosan Hussain)
- Land arrangement
- Joint development (JDA)
Promoter complaints
- Complaints on the promoter (total)
- 226
- Complaints on the promoter (pending)
- Not available
Sources
Karnataka RERA project page PRM/KA/RERA/1251/309/PR/311222/005591 (registration details, Uploaded Documents, Enquired Documents and Complaints tabs, and the quarterly updates for Q3 2025-26, Q4 2025-26, Q1 2026-27 and Q2 2026-27, checked 24 Oct 2026).
Things to know
- This record covers Phase 5 as registered on RERA (Wing 10) of the 10-wing Sobha Dream Gardens development; other phases are separate registrations and the common amenities are shared across the development.
- The launch date is the project start date declared on RERA (1 Oct 2023).
- RERA lists 142 apartments (74 one-bedroom of about 38 to 41 sq m carpet and 68 two-bedroom of about 58 sq m), matching the quarterly updates.
- Wing 10 has 17 floors above one basement.
- The land is held under a Joint Development Agreement registered on 6 Dec 2017, with the legal heirs of Zahed Husain (Sosan Hussain) as land owner and Sobha Limited as promoter.
- The khatha is an A Khatha issued by BBMP (26 Jul 2018) and the promoter's no-litigation affidavit is uploaded; no land litigation is declared.
- A file named CC is uploaded in the commencement certificate slot, so the certificate is shown as received.
- The occupancy certificate is not yet due (RERA completion 31 Dec 2028).
- The plan was approved by BBMP on 1 Oct 2018.
- Source of water is BWSSB.
- Land area is the total area declared (4,823 sq m). 164 covered parking spaces are declared.
- Total project cost is Rs 89.62 Cr: land Rs 29.43 Cr plus layout development Rs 60.20 Cr.
- FAR sanctioned is 2.381.
- Amenities listed for this phase are outdoor sports, a swimming pool and parks; the clubhouse and power backup are marked not applicable for this phase (they are shared in the wider development).
- Progress as filed was 61% (Q3 2025-26), 73% (Q4 2025-26), 77% (Q1 2026-27) and 97% (Q2 2026-27, filed 12 Oct 2026).
- Wing 10 is reported at 100% and every schedule item is at 100% except weather proof work, which is at 0% although its planned end date is 20 May 2026.
- Bookings shown by the quarterly updates moved from 137 (Q3 2025-26) to 140, 139 and 138 (Q2 2026-27) of 142 homes, as filed.
- The amount withdrawn from the RERA account was higher than the amount collected in Q4 2025-26 (Rs 17.97 Cr against Rs 17.77 Cr) and Q2 2026-27 (Rs 5.57 Cr against Rs 5.43 Cr), as filed, and lower in Q3 2025-26 and Q1 2026-27.
- RERA's Enquired Documents tab shows a query that the SEIAA environmental clearance did not mention Wing 10; a modified environmental clearance was uploaded on 28 Nov 2022.
- The Completion Details tab was not seen.
- RERA's Complaints tab (checked 24 Oct 2026) shows no complaints on this project and 226 on the promoter; how many of those are pending is not shown.
- Quarterly update compliance for earlier quarters not reviewed.
Verification
Last verified 24 Oct 2026