Nikoo Homes 8, Bhartiya Garden Enclave, Phase-1
By Bhartiya in Belahalli, Bengaluru, 560064
- Status
- Under construction
- Type
- Residential
- Locality
- Belahalli
- RERA completion
- 31 Mar 2031
- Total homes
- 518
- Last verified
- 8 Oct 2026
Summary
Approvals and checks: 8 clear, 3 to check, 0 problems. See the full list.
Construction is 38% complete as of 15 Jul 2026.
Project facts
- Type
- Residential
- RERA number
- PRM/KA/RERA/1251/309/PR/070526/008628
- Project start (per RERA)
- 1 Apr 2026
- Promised possession
- Not available
- RERA completion date
- 31 Mar 2031
- RERA extension
- No extension recorded
- Commencement certificate (CC)
- Not on RERA
- Occupancy certificate (OC)
- Not yet due
- Land area
- 7.54 acres69 homes per acre
- Open area
- 72.8% of the site
- FAR sanctioned
- 3
Location
Belahalli, Bengaluru, 560064
Approvals and checks
8 clear, 3 to check, 0 problems
- ✓RERA registrationRegistered
- ✓Building planApproved by BBMP
- !Commencement certificateNot uploaded on RERA
- –Occupancy certificateDue at completion
- ✓Environmental clearanceFiled on RERA
- ✓Fire NOCFiled on RERA
- ✓Airport height (AAI)Filed on RERA
- –Defence clearance (IAF)Not listed on RERA
- ✓Draft sale agreementPublished on RERA
- ✓Land litigationNone declared by promoter
- !Land ownershipJoint development with landowners
- ✓KhathaE Khatha
- !Court-records checkPending
Legal cases
Promoter declares no litigation on the land, property or khatha or on the project (non-litigation affidavit on RERA). Court records not yet checked independently.
Legal check not done yet. We have not completed a court-records check for this project.
RERA complaints
2 complaints on this project, 2 still pending.
What complaints were about
One complaint can raise several issues, so issues add up to more than the number of complaints.
By year filed
Disposed Pending
See all 2 complaints
- Refund of booking amount, booking made on a representation about home loan eligibility
- Booking token of Rs 1,00,000 not refunded after formal cancellation
Construction and sales
From the promoter’s latest RERA filing, as of 15 Jul 2026.
By tower
Construction complete Homes sold
A trend line appears here once the next quarterly update is added.
- Collected from buyers
- Rs 7.47 Cr
- Withdrawn from the RERA account
- Rs 0 Cr
- Total project cost (as declared on RERA)
- Rs 941.1 Cr
- Quarterly updates
- Up to dateLatest filed 15 Jul 2026
Construction timeline
Bars show the promoter’s planned dates on RERA. The vertical line is today. Colour shows progress from the promoter’s latest RERA filing.
98% complete
43% complete
Completed In progress Not started
Units
- Total homes
- 518
- Towers
- 4
- Floors (tallest tower)
- 24
- Unit types
- Studio, 1 BHK, 1.5 BHK, 2 BHK, 2.5 BHK, 3 BHK, 3.5 BHK, 4 BHK, Loft, 4 bed row house
- Unit sizes (carpet area)
- 345 to 2,535 sq ft
- Unit mix
- Studio: 15, 1 BHK: 38, 1.5 BHK: 15, 2 BHK: 67, 2.5 BHK: 136, 3 BHK: 126, 3.5 BHK: 67, 4 BHK: 17, Loft: 22, 4 bed row house: 15 (518 in total)
Price
- Price range
- Not available
- Price per sq ft
- Not available
Parking
- Covered parking
- 582 spaces1.12 spaces per home
Amenities
- Club house
- Community hall
- Outdoor sports
- Indoor sports
- Swimming pool
- Gym
- Parks
- Power backup
- CCTV
Living here
- Water source
- Borewell, Other
- Piped gas
- No
- Kitchen cabinets and wardrobes
- Not included, buyer fits them
- Clubhouse
- 28,309 sq ft55 sq ft per home
Promoter and land
- Builder (brand)
- Bhartiya
- Registered promoter
- Bhartiya Urban Pvt Ltd
- Land owner
- Liaquathulla Khan; Showkathulla Khan; Shujayathulla Khan; Maruthi H P; Bhimappa Handigund
- Land arrangement
- Joint development (JDA)
Promoter complaints
- Complaints on the promoter (total)
- 28
- Complaints on the promoter (pending)
- Not available
Sources
K-RERA project registration record (approved 07-05-2026), the K-RERA quarterly update for Q1 2026-27 (filed 15-07-2026), and the K-RERA complaints tab.
Things to know
- The registered promoter is Bhartiya Urban Pvt Ltd, which has 12 earlier RERA registrations in Karnataka, including Nikoo Homes II, IV, V and VI.
- The land is on 7 survey numbers in Belahalli village, Yelahanka Hobli, held by five landowners under a joint development agreement registered on 02-11-2019, with an E Khatha.
- The promoter has declared no litigation on the land, property or khatha or on the project.
- This is Phase 1 of a two-phase project with 4 blocks: towers D (16 floors), E and F (24 floors each) and a 2-floor block of 15 row houses.
- Tower D has 143 homes on the registration but only 111 in the Q1 update, so the update covers 486 homes against 518 registered.
- The update reports the project as 38% complete although every tower is at 0%, earth work is 98% done and foundation footing is 43% done, so the 38% figure should be read with care.
- Construction started ahead of the registered schedule.
- K-RERA lists 28 complaints on the promoter and 2 on this project, both filed in October 2026 about refunds of booking amounts and both awaiting an order.
- The registration lists 582 covered and 77 open parking spaces.
- Before approving, K-RERA asked the promoter to explain a mismatch between the CA and engineer cost figures, how loan money would be deposited in the project account, and the sources of funds, and the promoter replied on 29-04-2026.
- The document uploaded as the commencement certificate is a BDA work order dated 29-05-2025, and the relinquishment deed on file is a draft.
- The first quarterly update came after registration, so there is no earlier quarter to compare with.
- No sales agent is registered.
- Collections and sales are as declared by the promoter.
- Court records have not been checked independently.
Verification
Last verified 8 Oct 2026