Godrej Woodscapes
By Godrej Properties in Budigere Cross, Bengaluru, 560049
- Status
- Under construction
- Type
- Residential
- Locality
- Budigere Cross
- RERA completion
- 31 Jan 2029
- Total homes
- 2,168
- Last verified
- 4 Oct 2026
Summary
Approvals and checks: 8 clear, 2 to check, 0 problems. See the full list.
Construction is 26% complete as of 30 Jun 2026.
Project facts
- Type
- Residential
- RERA number
- PRM/KA/RERA/1251/446/PR/170524/006882
- Project start (per RERA)
- 31 Jan 2024
- Promised possession
- Not available
- RERA completion date
- 31 Jan 2029
- RERA extension
- No extension recorded
- Commencement certificate (CC)
- Not on RERA
- Occupancy certificate (OC)
- Not yet due
- Land area
- 11.21 acres193 homes per acre
- Open area
- 77.5% of the site
- FAR sanctioned
- 3.25
Location
Budigere Cross, Bengaluru, 560049
Approvals and checks
8 clear, 2 to check, 0 problems
- ✓RERA registrationRegistered
- ✓Building planApproved by BDA
- !Commencement certificateNot uploaded on RERA
- –Occupancy certificateDue at completion
- –Environmental clearanceNot listed on RERA
- ✓Fire NOCFiled on RERA
- ✓Airport height (AAI)Filed on RERA
- –Defence clearance (IAF)Not listed on RERA
- ✓Draft sale agreementPublished on RERA
- ✓Land litigationNone declared by promoter
- ✓Land ownershipPromoter's own land
- ✓KhathaE Khatha
- !Court-records checkPending
Legal cases
The promoter declares no litigation on the land, khatha or project, with a non-litigation affidavit uploaded. Five RERA complaints have been filed against this project since January 2024, and all five are disposed (one by the full bench of the Authority and four by Authority Bench 4). They concern the carpet area given, the cancellation of an allotment and use of funds, changes to the approved plan including a retail block turned into residential towers, and registration under Section 3. The outcomes are not shown on the page. We have not yet done a court-records check. Last checked: 4 Oct 2026.
Legal check not done yet. We have not completed a court-records check for this project.
RERA complaints
5 complaints on this project.
What complaints were about
One complaint can raise several issues, so issues add up to more than the number of complaints.
By year filed
Disposed Pending
See all 5 complaints
- Alleged unauthorised change of a retail block (G+3) into residential Towers R and S (G+38)
- Significant changes to the approved plan without prior consent of existing flat buyers
- Cancellation of allotment and alleged misuse of funds
- Area promised for the selected unit was 170.1 sq m, but 115.29 sq m was given
- Alleged violation of Sections 3, 7, 9 and 10 of the RERA Act; service fees and compensation claimed under Section 69
Construction and sales
From the promoter’s latest RERA filing, as of 30 Jun 2026.
By tower
Construction complete Homes sold
Over time
Construction complete Homes sold
- Collected from buyers
- Rs 59.49 Cr
- Withdrawn from the RERA account
- Rs 36.49 Cr
- Total project cost (as declared on RERA)
- Rs 2,358.26 Cr
- Quarterly updates
- Up to dateLatest filed 10 Jul 2026
Construction timeline
Bars show the promoter’s planned dates on RERA. The vertical line is today. Colour shows progress from the promoter’s latest RERA filing.
RERA items combined: earthwork and levelling (92% done); foundation footing (91% done). Both were due to finish by 27 Sep 2024 and 26 Dec 2024.
RERA items combined: retaining wall (7%); up to plinth level (7%); sub-structure flooring for parking floors (20%). The retaining wall and plinth were due by 8 Apr and 8 May 2025.
RERA items combined: RCC or MS framed structure (7%, planned 8 Apr 2025 to 10 Apr 2027); masonry (0%). Slabs are complete to the 8th floor in the most advanced tower.
RERA items combined: basic water, sanitary and electrical work; plastering; joinery; flooring and tiles; railing; finishing fittings; painting; fire fittings; weatherproofing; elevation. All at 0%.
Internal and external works including landscaping, at 0%. The planned end, 4 Mar 2029, is after the RERA completion date of 31 Jan 2029.
Completed In progress Not started
Units
- Total homes
- 2,168
- Towers
- 13
- Floors (tallest tower)
- 39
- Unit types
- 1 BHK, 2 BHK, 2.5 BHK, 3 BHK, 4 BHK, 1BT-EWS
- Unit sizes (carpet area)
- 491 to 1,732 sq ft
- Unit mix
- 3 BHK: 1434; 2 BHK: 480; 1BT-EWS: 160; 4 BHK: 77; 2.5 BHK: 11; 1 BHK: 6
Price
- Price range
- Not available
- Price per sq ft
- Not available
Parking
- Covered parking
- 2,257 spaces1.04 spaces per home
Amenities
- Clubhouse
- Swimming pool
- Gym
- Indoor sports
- Outdoor sports
- Parks
- CCTV
- Power backup
- Sewage treatment plant
- Rainwater harvesting
- Renewable energy
Living here
- Water source
- Other
- Piped gas
- No
- Kitchen cabinets and wardrobes
- Not included, buyer fits them
- Clubhouse
- 80,729 sq ft37 sq ft per home
Promoter and land
- Builder (brand)
- Godrej Properties
- Registered promoter
- Godrej Properties Limited
- Land owner
- Godrej Properties Limited
- Land arrangement
- Own land
Sources
Karnataka RERA project page for Godrej Woodscapes (registration PRM/KA/RERA/1251/446/PR/170524/006882; checked 4 Oct 2026) and its Q3 2025-26, Q4 2025-26 and Q1 2026-27 quarterly updates (filed 14 Jan, 13 Apr and 10 Jul 2026; latest progress as of 30 Jun 2026).
Things to know
- This registration is Phase 1 of the Godrej Woodscapes development (the RERA forms are labelled Phase 1): 13 towers and 2,168 homes on 11.21 acres.
- The promoter's list on RERA shows two more registrations for the development, Godrej Woodscapes Phase 2 and Boulevard at Godrej Woodscapes.
- They are not part of this record.
- The launch date is the project start date declared on RERA, and no extension is shown.
- Land area is the RERA project area of 45,352 sq m.
- Unit sizes are RERA carpet areas from the flat-wise table. 160 homes are listed as 1BT-EWS with carpet areas of 9.6 to 11.6 sq m, and the smallest and largest sizes shown leave them out.
- The commencement certificate slot says Not available.
- The plan was approved by BDA on 29 Sep 2023.
- The agreement for sale proforma was added in April 2025 under additional documents.
- A fire NOC is uploaded under other documents.
- The KSPCB approval is shown as approved in the quarterly updates, but its document slot is empty, and the environmental clearance (MoEF) is marked not applicable.
- Water comes from the local panchayat.
- The filing reports 26% overall completion, but work-wise progress in the same filing is lower: RCC frame 7%, plinth level 7%, foundations 91%.
- Slabs are complete up to the 8th floor in the most advanced tower.
- The planned end dates for earthwork, foundations, plinth and the retaining wall have passed.
- The last planned milestone ends on 4 Mar 2029, after the RERA completion date of 31 Jan 2029.
- The filing reports Rs 42.92 Cr of principal and interest payable to an NBFC, for which nothing was budgeted, and consultants' fees of Rs 94.04 Cr against Rs 57.11 Cr budgeted.
- Construction cost spent is Rs 212.53 Cr of the engineer-certified Rs 1,584.67 Cr.
- Buyer advances and RERA account withdrawals do not move consistently from one filing to the next (withdrawals of Rs 222.75 Cr, Rs 167.24 Cr and Rs 36.49 Cr), so they appear to be reported on different bases.
- The 'actual' start dates for most works equal the planned dates and are not used.
- The K-RERA complaints tab lists five complaints on this project, checked 4 Oct 2026.
- One of them, 00058/2024, is listed under the project's earlier name, Godrej Budigere Cross / Godrej Bengal Lamps.
Verification
Last verified 4 Oct 2026