Elara Celestia
By L&T Realty in Hebbal, Bengaluru, 560092
- Status
- Under construction
- Type
- Residential
- Locality
- Hebbal
- RERA completion
- 31 Mar 2030
- Total homes
- 634
- Last verified
- 27 Sept 2026
Summary
Approvals and checks: 10 clear, 2 to check, 0 problems. See the full list.
Construction is 18% complete as of 30 Jun 2026.
Project facts
- Type
- Residential
- RERA number
- PRM/KA/RERA/1251/472/PR/100325/007564
- Project start (per RERA)
- 15 Feb 2025
- Promised possession
- Not available
- RERA completion date
- 31 Mar 2030
- RERA extension
- No extension recorded
- Commencement certificate (CC)
- Not on RERA
- Occupancy certificate (OC)
- Not yet due
- Land area
- 10.07 acres63 homes per acre
- Open area
- 74.4% of the site
- FAR sanctioned
- 3.25
Location
Hebbal, Bengaluru, 560092
Approvals and checks
10 clear, 2 to check, 0 problems
- ✓RERA registrationRegistered
- ✓Building planApproved by BBMP
- !Commencement certificateNot uploaded on RERA
- –Occupancy certificateDue at completion
- ✓Environmental clearanceFiled on RERA
- ✓Fire NOCFiled on RERA
- ✓Airport height (AAI)Filed on RERA
- ✓Defence clearance (IAF)Filed on RERA
- ✓Draft sale agreementPublished on RERA
- ✓Land litigationNone declared by promoter
- ✓Land ownershipPromoter's own land
- ✓KhathaE Khatha
- !Court-records checkRERA cases recorded, court search pending
Legal cases
The Raintree Boulevard Apartment Owners Association challenged Elara Celestia's RERA registration, alleging that L&T changed the township's development plan without the consent of existing residents. K-RERA dismissed the complaint (No. 00772/2025) on 15 April 2026, and the Karnataka Real Estate Appellate Tribunal dismissed the appeal (No. 63/2026) on 27 August 2026, confirming that the project's registration stands. A further appeal to the High Court was possible within 60 days of the Tribunal's order. Last checked: 27 September 2026.
2 cases on record, all disposed. A full court-records search has not been done yet.
Dismissed on 15 Apr 2026. Filed by the Raintree Boulevard Apartment Owners Association.
Dismissed on 27 Aug 2026, confirming K-RERA's order.
RERA complaints
1 complaint on this project.
What complaints were about
One complaint can raise several issues, so issues add up to more than the number of complaints.
By year filed
Disposed Pending
See all 1 complaint
- Challenge to registration; plan changes without allottee consent (dismissed; appeal dismissed)
Construction and sales
From the promoter’s latest RERA filing, as of 30 Jun 2026.
By tower
Construction complete Homes sold
A trend line appears here once the next quarterly update is added.
- Collected from buyers
- Rs 148.07 Cr
- Withdrawn from the RERA account
- Rs 100.12 Cr
- Total project cost (as declared on RERA)
- Rs 1,576.76 Cr
- Quarterly updates
- Up to dateLatest filed 14 Jul 2026
Construction timeline
Bars show the promoter’s planned dates on RERA. The vertical line is today. Colour shows progress from the promoter’s latest RERA filing.
Completed. Foundations began in Sep 2025, about 4 months ahead of plan.
As of Jun 2026: basement floors 93% done, retaining walls 25%.
As of Jun 2026: frame 6% done. It began in Jan 2026, well ahead of the planned May 2027 start. Towers have reached between the ground and 3rd floor.
Planned to finish on the RERA completion date, 31 Mar 2030, with no buffer.
Completed In progress Not started
Units
- Total homes
- 634
- Towers
- 3
- Floors (tallest tower)
- 13
- Unit types
- 1 BHK, 2 BHK, 3 BHK, 4 BHK, 4 BHK duplex, 5 BHK duplex
- Unit sizes (carpet area)
- 645 to 3,532 sq ft
- Unit mix
- 3 BHK: 466; 4 BHK: 144; 5 BHK duplex: 7; 4 BHK duplex: 2; 2 BHK special: 8; 3 BHK special: 3; 1 BHK special: 4
Price
- Price range
- From Rs 4 Cr (L&T website)
- Price per sq ft
- Not available
Parking
- Covered parking
- 862 spaces1.36 spaces per home
Amenities
- Clubhouse
- Swimming pool
- Gym
- Indoor sports
- Outdoor sports
- Parks
- CCTV
- Power backup
- Air conditioning
- Sewage treatment plant
- Rainwater harvesting
- Renewable energy
Living here
- Water source
- BWSSB, Tanker
- Piped gas
- No
- Kitchen cabinets and wardrobes
- Not included, buyer fits them
- Clubhouse
- 25,306 sq ft40 sq ft per home
Promoter and land
- Builder (brand)
- L&T Realty
- Registered promoter
- L&T Realty Developers Limited (formerly L&T Construction Equipment Ltd)
- Land owner
- Larsen & Toubro Limited
- Land arrangement
- Own land
Promoter complaints
- Complaints on the promoter (total)
- 21
- Complaints on the promoter (pending)
- 1
Sources
Karnataka RERA project page PRM/KA/RERA/1251/472/PR/100325/007564 (all tabs, checked 27 Sep 2026); L&T Realty website; K-RERA order in complaint 00772/2025 (15 Apr 2026); Appellate Tribunal order in appeal 63/2026 (27 Aug 2026).
Things to know
- The launch date is the project start date declared on RERA.
- The commencement certificate is not uploaded on RERA (a BDA development plan sits in its place); the BBMP building licence of 4 Mar 2025 is uploaded.
- RERA lists 862 covered parking spaces, but the tower-level figures add up to 720.
- The largest unit size is the average for the 5 BHK duplex type.
- Quarterly updates for Apr to Sep 2025 are not listed on RERA.
- Former name of the promoter: L&T Construction Equipment Ltd.
Verification
Last verified 27 Sept 2026